Licensed Demolition & Excavation Experts. Servicing Greater Melbourne.
info@demolitionmasters.com.au 0451 111 115
Process & Planning

How Long Does It Take to Demolish a House in Melbourne?

The actual on-site demolition is the fastest part. Here is the full timeline, including the steps before and after the machine moves in.

Most of the time you spend demolishing a house in Melbourne is not spent demolishing. The actual machine-on-site work is a small slice of the total project — typically 3–10 working days. The other six to twelve weeks are permits, paperwork, asbestos surveys, service disconnections, and handover. Here is the realistic timeline.

The two timelines

It helps to separate two different questions:

  1. How long from contract to handover? Usually 6–12 weeks.
  2. How long are crews actually on site? Usually 3–14 working days.

The first one matters for builder coordination. The second one matters for noise, neighbour relations, and disruption.

Pre-demolition phase — usually 4–7 weeks

Permits (2–4 weeks)

A demolition building permit issued by a private surveyor takes 2–4 weeks. If a planning permit is also required (for example, due to heritage overlay), add 4–12 weeks on top. Permit detail here.

Asbestos survey (1 week)

A licensed assessor takes samples and the lab returns results in around five business days. Required for almost all pre-1990 Melbourne homes.

Service disconnections (3–6 weeks)

Each utility provider has its own timeline:

  • Electricity disconnection: 2–4 weeks
  • Gas abolishment (full removal of meter and service): 4–6 weeks
  • Water disconnection: 1–2 weeks
  • Sewer cap-off: 1–2 weeks
  • NBN/telecom: 1–2 weeks

Gas is almost always the bottleneck. Start early.

Asset protection bond (1–2 weeks)

Most councils require a refundable bond before demolition. Lodgement is usually quick once the form is in.

On-site demolition — actual machine days

Once everything is in place, the machines move in. Realistic working-day estimates for the structural demolition:

PropertyDays on site
Single-storey weatherboard2–3 days
Single-storey brick veneer3–5 days
Double-storey brick veneer5–7 days
Double-storey solid brick6–9 days
Heritage / facade retention10–20 days
Tight inner-city access+30–50% time
Heavy asbestos load+3–5 days for soft strip

Why two demolitions of similar size take very different time

Five common multipliers:

Side passage width

A 14-tonne excavator can clear a single-storey home in 2 days. A 5-tonne mini, used because the side passage is narrow, takes 4–5 days for the same building. Narrow lot techniques.

Truck rotation

A site that can stage two trucks at once moves twice the volume per hour as a site that can only fit one. Front-only access in tight streets often means single-truck rotation.

Asbestos load

Bonded asbestos in eaves and bathroom adds a day to soft strip. Friable (Class A) material adds significantly more — full containment, negative-pressure enclosures, and clearance certificates between stages.

Slab thickness and reinforcement

Some older slabs are surprisingly thick. Others have heavy reinforcement, multiple repair layers, or buried plumbing. What looks like a half-day slab break can become two days.

Adjoining structures

Demolishing back-to-front to protect a retained facade, or working carefully along a shared boundary wall, slows the pace deliberately. This is a feature, not a bug — but it lengthens the calendar.

Buffer your build

If your demolition is timed against a builder's slab pour, build in 1–2 weeks of buffer. Permits can stretch, weather days happen, and asbestos surprises occur. A buffer is cheaper than a slab pour reschedule.

What can the homeowner do to speed things up?

The contractor controls most of the timeline, but the homeowner has three meaningful levers:

  1. Start service disconnections immediately on signing. Don't wait for the permit to come through. Gas in particular has the longest lead time.
  2. Get the asbestos sampling done early. Even before the contract is signed if possible — it removes the biggest source of mid-job variation.
  3. Be reachable. Permits, council questions, and bond paperwork sometimes need a quick yes from the homeowner. A 24-hour response saves three days; a week-long delay can add two weeks.

Weather and Melbourne winters

Demolition continues through Melbourne winters with one major caveat: heavy rain pauses the work. Wet sites are unsafe for tracked machines on tight ground, and dust suppression becomes mud suppression. A typical Melbourne winter project loses 1–3 days to weather. Build that into your plan.

Holiday windows

If your project runs through Christmas, expect a closure of 2–3 weeks across most contractors and council offices. Easter and the Australia Day long weekend each cost a few days. Plan around them or accept the extension.

Total realistic timing

A clean, simple, single-storey suburban demolition from signed contract to handover: 6–8 weeks. A complex, heritage-overlay, double-storey project: 12–16 weeks. Builder-coordinated knockdown rebuilds: read the integration timing here.

Anyone quoting "we'll have it done in two weeks" is either describing the on-site work only, or is missing significant pre-demolition steps. Ask which one they mean.

Ready to
Clear the Site?

Follow Our Work

Latest On @DemolitionMasters.

Site updates, before-and-afters, and the gear we run — straight from our crews.

Call Now Get a Quote
WhatsApp